Project Summary
Saulsbury was awarded the fabrication, mechanical, and electrical and instrumentation contracts for the environmental retrofit including installation of two air pollution control systems of a client’s 1,650-MW coal-fired power plant in Northeast Texas. The construction team fabricated all ductwork, constructed the facility, and provided overall project supervision and craft labor.
—
Electrical, mechanical, & Civil Services
Saulsbury provided the labor, supervision, administration, management, tools, installation, and testing equipment required for the following:
- Structural mechanical baghouse installation
- Environmental Retrofit
- ACI/FF/Chimney project
- On-site ductwork fabrication
- Ductwork appurtenances—turning vanes, bracing and stiffeners, instrument connections, and probe supports
- Supply and installation of ductwork insulation
—
Electrical & Instrumentation Installation
The environmental retrofit for electrical work included all raceways, conduit, wire, termination, grounding, and equipment for the following:
- Balance of plant
- Fabric filter
- Ash handling system
- All associated DCS, activated carbon injection, CEMS (emissions control), mill inerting, and pre-outage and outage work
- Compression and dryers